In short
- Italy’s 2026 hyper-depreciation (Law 199/2025) increases the depreciable cost of Industry 4.0 assets by 180% up to €2.5 million, by 100% up to €10 million and by 50% up to €20 million, for investments made from 1 January 2026 to 30 September 2028.
- Software only qualifies if it is listed in Annex V and is interconnected with the production management system: a purely administrative ERP is left out.
- SaaS subscriptions are excluded: what counts is a licence recorded as a fixed asset.
- You need notifications to the GSE, a sworn appraisal and an accounting certification, whatever the amount. Plan the project first, then buy.
Reading time: 6 minutes
Every time an incentive comes along, the same thing happens in companies: people rush to buy before it ends. It is the deadline effect: faced with a benefit that expires, we tend to favour the immediate advantage over the quality of the choice. Psychologists call it present bias.
With software this reflex is expensive. A program bought in a hurry and never really integrated does not qualify for the benefit, and above all it does not improve production. Let’s look at how the measure works and how to set up a project that holds up both on the shop floor and during a tax inspection.
How the 2026 hyper-depreciation works
It is not a tax credit: it is an increase in the tax-depreciable cost, which reduces taxable income for IRES or IRPEF (Italian corporate and personal income tax). So it only works if the company has taxable income. It only concerns taxpayers with business income: public bodies and professional associations cannot use it.
The law (art. 1, paragraphs 427-436, Law 199/2025) sets three brackets:
- 180% on the portion of investment up to €2.5 million;
- 100% above €2.5 million and up to €10 million;
- 50% above €10 million and up to €20 million.
The requirement for assets to be produced in the EU or EEA was removed by Decree-Law 38/2026 with effect from 1 January 2026. It remains only for photovoltaic modules. The final text of the law does not include the additional increase for the green transition that appeared in the first draft.
Which software qualifies for hyper-depreciation (and which doesn’t)?
Annex V follows the logic of the old Annex B of Industry 4.0. The main items include:
- MES, SCADA and maintenance software (CMMS), i.e. managing and coordinating production;
- product design and lifecycle (PLM, simulation, digital twin);
- process quality, dispatching and product routing;
- integrated factory logistics and supply chain;
- cybersecurity for networks, machines and plants;
- site energy management, industrial IoT and production data analysis;
- artificial intelligence applied to processes: generative AI, agentic AI, predictive maintenance, process mining.
What is left out: accounting, invoicing, CRM, administrative ERP and, in general, software not connected to the production site. An ERP module that plans production and exchanges data with machines may qualify, if it meets the requirements. Functions and interconnection decide, not the product name.
SaaS, cloud and AI: what applies today?
The benefit works through depreciation, so you need an asset recorded among intangible fixed assets: a perpetual licence or a capitalised multi-year right of use, also for software installed on premises. The implementing decree left out SaaS subscriptions, because they are a service and not an asset. So not all modern software is excluded: subscriptions are excluded, capitalisable licences are not.
The same goes for AI: it qualifies as process software, not as a generic subscription. Among the most widely used assistants, such as ChatGPT, Claude, Copilot, Gemini and Mistral’s Le Chat, an office subscription is not an Industry 4.0 asset.
Implementing decree and GSE notifications: where are we?
The MIMIT-MEF implementing decree of 7 May 2026 is available on the Ministry’s website. The procedure goes through the platform of the GSE (the Italian energy services operator):
- Advance notification (open since 12 June 2026), for each production facility, to be sent before the order;
- Confirmation within 60 days of the positive outcome, with a down payment of at least 20% for each asset;
- Completion by 15 November 2028, with invoices, a sworn technical appraisal and an accounting certification;
- Periodic monitoring notifications every year.
The increase applies from the tax period in which the investment is completed, provided the asset is in operation and interconnected in the same year.
A practical calculation example
Hypothetical example, for illustration only. A company buys MES software licences for €200,000, recorded as fixed assets and interconnected with production. Whether, and to what extent, integration and custom development costs also qualify must be checked case by case. With the 180% increase, the tax-depreciable cost rises to €560,000. Note: the deduction is not the saving. With ordinary IRES at 24%, the extra €360,000 of deduction is worth about €86,400 less in taxes, spread over the depreciation years. The real calculation depends on the company’s situation: check it with your accountant.
Interconnection: why “having a server” is not enough
Interconnected means that the software exchanges data automatically and in a documented way with the production management system or with the supply network.
We once worked with a company with several sites that had a central server, but part of the data stayed on the PCs of individual sites and was not replicated. Having “a server” does not mean having centralised data. In a case like this an appraiser will struggle to certify a data flow that, in practice, breaks off.
What the 2027 Budget Law provides
The 2027 Budget Bill was approved by the Council of Ministers on 28 October 2026 and is now before Parliament. It is not law yet and the text may change: final approval is expected by 31 December 2026. In the text presented, hyper-depreciation is not changed: it remains as set by the 2026 Budget Law, valid for investments made by 30 September 2028.
The new measure most relevant to software is a 30% tax credit on subscriptions to cloud solutions, for costs incurred in 2027, 2028 and 2029, with an overall cap of €30 million a year and rules to be set by an implementing decree. It is designed precisely for subscription software, which remains excluded from hyper-depreciation. Before planning, it is worth waiting for the final text: we will update this article once the law is approved.
How to set up an ERP, MES or integration project
Before signing, ask your supplier for:
- a map of data flows between software, machines and existing systems;
- technical documentation of the interconnection (protocols, APIs, exchange logs);
- a technical report useful to the appraiser;
- a clear distinction between capitalisable licences and subscription services.
Quick checklist
- Does the software fall under an Annex V item?
- Is it connected to a production facility in Italy?
- Can the licence be recorded as a fixed asset?
- Advance notification sent before the order?
- 20% down payment and confirmation on time?
- Interconnection active and documented by year end?
- Appraiser and auditor involved from the start?
- Accountant informed about timing and amounts?
Which sectors can benefit most?
- Mechanical engineering and subcontracting: MES, traceability and predictive maintenance;
- Food: process quality and batch traceability;
- Packaging: line monitoring and energy management;
- Warehouse logistics: WMS integrated with production and shipping.
How we work
At SWD Group we design ERP systems, custom software and integrations with interconnection documented from the start: flows, protocols, checks. We work alongside your accountant and appraiser, each in their own role. We do not give tax advice: we provide the technical part that those who give it need.
If you are considering a project, we can set aside a 30-minute call to see whether the approach holds up.
Frequently asked questions
How does hyper-depreciation 2026 work? It increases the depreciable cost of Industry 4.0 assets by 180%, 100% or 50% depending on the bracket, reducing taxable income over the depreciation years. It only applies to taxpayers with business income.
How is hyper-depreciation calculated? You apply the bracket percentage to the cost of the asset: €200,000 at 180% generates €360,000 of additional deduction. The deduction is not the saving: with IRES (corporate income tax) at 24%, taxes go down by about €86,400, spread over the depreciation years. The calculation should be checked with your accountant.
Does an ERP qualify for hyper-depreciation? Only for the functions listed in Annex V and linked to production, with demonstrable interconnection. Accounting, invoicing and CRM do not qualify.
Do cloud or SaaS software qualify? Not under hyper-depreciation: SaaS subscriptions are excluded; what counts are licences recorded as fixed assets. The 2027 Budget Bill, still under discussion, provides a separate 30% tax credit for cloud subscriptions.
Is the sworn appraisal always required? Yes: the sworn technical appraisal and the accounting certification are required for any amount.
Let’s talk
Want to know whether your software project could qualify? Book a 30-minute call or write to us at posta@swdweb.it.
The information in this article is for general information only and does not constitute tax advice: every assessment should be checked with your own accountant. Updated on 3 November 2026.
Leonardo Pantaleo, CEO of SWD Group
Sources (in Italian)
- Annex V to Law 199/2025 (Official Gazette no. 301 of 30/12/2025), copy published by Innovation Post
- NT+ Fisco – Il Sole 24 Ore, on software linked to the production site (19/01/2026)
- Agenda Digitale, guide to hyper-depreciation 2026 and GSE notifications
- Euroconference News, “no to SaaS, yes to licences”
- Euroconference News, end of the EU/EEA origin requirement (Decree-Law 38/2026)
- ANCE, launch of the GSE platform and implementing decree (12/06/2026)
- AssoSoftware, analysis of the implementing decree
- Eutekne, tax credit for cloud software in the 2027 Budget Bill (03/11/2026)
- Agenda Digitale, all the 2027 Budget Law measures for business, work and digital